Re: SVOs do not have planned cost

$
0
0

There could be many reasons.

 

  1. If its internal activity, check the work center, cost center assigned in work center, activity type in service order & activity price maintained in KP26
  2. If its External activity, check whether you have maintained the price in External tab of operations details screen
  3. Check the Control Key settings whether "Cost" tick mark has been selected or not.
  4. Check the Costing variant assignment to your service order under Control tab of Service order