Hi All,
I have this situation where for the Component[Dependent Requirements] --> Requirement date is different for Planned Order from the DepReq line in MD04. As in below screen, the DepReq date is 11.03.2015 and the generated Planned Order is working with 31.03.2015, this cause some major issues with Planned Order Scheduling. The question is, what could be the root cause for this and how to fix this ?
When I look at the Order report for this dependent Requirement it shows the Planned Order marked with exception message 10[I understand what Rescheduling is and that it works with firm replenishment orders]. See below:
Below is screen of Pegged requirement for the Planned Order:
The Individual/Collective requirement at all the Levels is set to 1. The Planning strategy set to 40.
Please let me know if any further data would be required.
Regards,
Avinash